Dear
Growers
We
are now into the third week and appears the mill is struggling
with some operational and Transport issues including locos
breaking down. CANEGROWERS Herbert River are endeavouring to work
with mill management to ensure communication is more forthright and
transparent.
This
is appearing more challenging than first anticipated.
The
mill has reported that Standover quality has had an impact on
rates last couple of weeks. There has been stand over CCS as low
as 3s. The mill has reported that this is un-mill able.
As
you are aware last week was a wet one which gave the mill an
opportunity to bring forward some cleaning and maintenance work.
The
next maintenance and cleaning is tentatively planned for
Tuesday 18th July for Victoria and each Tuesday
thereafter. And for Macknade it is tentatively planned for 27th
July and for each 3rd Thursday thereafter. The mill
advised that the planned loading should correspond.
The
mill reported that they have taken the opportunity during the wet
stop to get ahead on loco servicing, mud processing plant
maintenance, evaporator cleaning (rate impact) and other routine
maintenance activities.
3
locos are getting close attention from the OEM to ensure they
have a reliable fleet going forward.
I have been
assisting Members with incorrect CCS and have been successful in
getting the right outcome and results for members. If you do need
assistance with CCS adjustments due to incorrect allocation
please do not hesitate to contact me.
Please ensure your
harvester contractor is writing finish times on bin tickets.
Frank
Scardamaglia
Manager